2nd
Strelasund Crossing, Stralsund, Germany
|
| |
|
|

|
|
The project: Construction
of the second Strelasund crossing
Executing company:
Max Bögl Bauunternehmung GmbH & Co. KG
|
| |
|
|
|
The Strelasund crossing,
which is 4.100 metres long, consists of several bridges and dam
structures. These include the 580 metre long cable-stayed bridge that
crosses the Ziegelgraben. An enormous, 128 metre tall yet elegant pylon
structure makes the cable-stayed bridge a captivating piece of
architecture that is certainly the most prominent structure of the
crossing. The Stralsund (645m) and Dänholm (530m) approach viaducts
connect on both sides in addition to the structures over the Strelasund
(1.070 m).
The problem:
Pumping off
the water and concrete mixture created in the course of boring piles
that are 900mm in diameter at a depth of up to 50m into the ground for
soil stabilization.
|
|

|
| |
|
|
 |
|
Our
solution: Use of two
KTZ411 units for securing the boring piles during the casting phase.
These units are used to pump out the mixture of water and concrete.
 |
| |
|
|
In the
event of abrasive and corrosive utilization, stronger wear and tear will
take place naturally in certain components. With regards to the above
application wear and tear can take place mainly in impeller,
suction plate, shaft sleeve, oil ring, mechanical seal, pump casing,
strainer, motor casing and discharge coupling. Depending on the working
conditions the lifetime of those parts might vary significantly and can
be shorter than the legal warranty period.
In this regard, please pay attention to our
general conditions of sales
(www.tsurumi-europe.com/english/GCS.htm) that we also
send to you by mail on request. |
|