Project:
Construction of an underground railway tunnel with a length of 130 m,
descending heading with a partial cut machine.
Executing companies:
ARGE Tunnel Weißenburger Straße, Dortmund
Wiemer & Trachte AG
Alpine Bau Deutschland GmbH
The Problem:
Drainage during the tunnel heading work. |
| |
|
|
| Our
Solution:
Use of submersible pumps of the KTZ series which can reliably ensure
drainage in 24-hour snore mode during the heading work.
|
|

Portal with partial cut
machine in operation |
| |
|
|
|

Collecting shaft with
KTZ47.5 and KTZ35.5 in operation in snore mode |
| |
|
|
In the
event of abrasive and corrosive utilization, stronger wear and tear will
take place naturally in certain components. With regards to the above
application wear and tear can take place mainly in impeller, agitator,
suction plate, shaft sleeve, oil ring, mechanical seal, pump casing,
strainer, motor casing and discharge coupling. Depending on the working
conditions the lifetime of those parts might vary significantly and can
be shorter than the legal warranty period.