Construction of an office building, Spreeport |
| |
|
|
|
 |
|
The
Project:
Construction of an office building, 1st construction phase
Executing company:
HOCHTIEF Construction AG, Niederlassung Berlin
Responsible for setting up the construction site and for the technical
equipment:
STREIF Baulogistik GmbH, Niederlassung Ost
The Problem:
Pumping off the storm water arising on the roofs during the construction
phase. |
| |
|
|
| Our
Solution:
Eight type KTVE21.5 pumps with integrated electrode controls were
installed in the shafts. The slim electrodes, which are attached,
replace float sensors which take a lot of space and are
maintenance-intensive. Only the motor line of the pump has to be relaid;
no additional cables for float switches have to be connected. |
|
 |
| |
|
|
In the
event of abrasive and corrosive utilization, stronger wear and tear will
take place naturally in certain components. With regards to the above
application wear and tear can take place mainly in impeller, suction
plate, shaft sleeve, oil ring, mechanical seal, pump casing, strainer,
motor casing and discharge coupling. Depending on the working conditions
the lifetime of those parts might vary significantly and can be shorter
than the legal warranty period.
In this regard, please pay attention to our
general conditions of sales
(www.tsurumi-europe.com/english/GCS.htm) that we also
send to you by mail on request. |
|