City
railway tunnel, Dortmund |
| |
|
|
|
 |
|
The
project:
Construction of the city railway station Ostentor
Executing company:
Wayss & Freytag Ingenieurbau AG
Oevermann GmbH
The problem:
Pumping off the water arising during mined underground heading. |
| |
|
|
Our
solution:
10 Tsurumi
submersible waste water pumps of series KTZ were used for drainage. In
the illustration above one KTZ45.5 and one KTZ67.5 are shown on snore
operation installed in the starting shaft. The tunnel is driven on two
levels over a length of 1300m and a cross section from 36sqm up to
185sqm. Track 3 at level 21m under ground passes below the track 2
running at level 14m underground and surfaces between the tunnels for
tracks 1 and 2. |
|
 |
| |
|
|
In the
event of abrasive and corrosive utilization, stronger wear and tear will
take place naturally in certain components. With regards to the above
application wear and tear can take place mainly in impeller, suction
plate, shaft sleeve, oil ring, mechanical seal, pump casing, strainer,
motor casing and discharge coupling. Depending on the working conditions
the lifetime of those parts might vary significantly and can be shorter
than the legal warranty period.
In this regard, please pay attention to our
general conditions of sales
(www.tsurumi-europe.com/english/GCS.htm) that we also
send to you by mail on request. |
|