Pipe
heading Aakerfährstraße, Germany |
| |
|
|
|
 |
|
The
Project:
Pipe heading DN1200 Aakerfährstraße, Duisburg, Germany
Executing company:
Siebert Bauunternehmung GmbH, Bebra
The Problem:
Lowering and maintaining the groundwater table. At the beginning several
medium-sized pumps were employed |
| |
|
|
| which
burdened the mains electricity supply excessively. As the river Rhine
flows past at a distance of 200m the groundwater could only be lowered
with difficulty.
Our Solution:
A pump of type
KRS2-89 incl. hosepipe and 300m drainage in the form of a pipe. Draining
of the excavation for the whole construction period. Operation of the
pump in 24-hour pumping on snore mode. |
|
 |
| |
|
|
In the
event of abrasive and corrosive utilization, stronger wear and tear will
take place naturally in certain components. With regards to the above
application wear and tear can take place mainly in impeller, suction
plate, shaft sleeve, oil ring and mechanical seal. Depending on the
working conditions the lifetime of those parts might vary significantly
and can be shorter than the legal warranty period.